Local 1245 members working for Black & Veatch are giving San Francisco’s electric reliability a big boost as they complete a new 115kv transmission line.
The project connects PG&E’s Martin and Hunters Point substations. The Black & Veatch crews are pulling in and splicing cable, using conduit installed earlier this year by Local 1245 members at Underground Constructors.
Trenching work by Underground Constructors was featured in the July/August 2008 Utility Reporter and can be viewed on-line at www.ibew1245.com/Group_Profiles/Underground_Constructors_8-7-08.pdf